Planning conditions

How much does discharging planning conditions cost in London?

Permission is not the end: the conditions on it can stop a start on site, and each request to clear them has its own council fee.

By Ben Shaukat, Managing DirectorPublished 2 min read

Get a fixed fee for your house

We will send your fixed fee here.

Handy if a quick call is easier.

We check conservation areas and other limits for this address.

In a sentence or two: your plans, and any feedback from the council so far.

Optional. PDF, JPG, PNG, HEIC or DWG. Up to 10 files, 28 MB in total.

Write before 3pm and you hear back that working day.

We use your details only to answer this enquiry. Read our privacy notice.

Prefer WhatsApp? Send us a message · +44 7592 201353

What a condition is, and why it can stop you starting

A planning permission often comes with conditions: details of materials, a drainage design, a construction method, tree protection. Some say nothing may begin until the council has approved what they ask for. Those are pre-commencement conditions.

The planning guidance is blunt about the risk. Development carried out without complying with a pre-commencement condition would be unlawful and may be the subject of enforcement action. So the discharge happens before the builder mobilises, not after.

From first enquiry to a planning decisionA vertical timeline of eight steps: enquiry and constraints check, measured survey, drawings in about 7 days after the survey, you approve the design, an independent check by a second technologist, submission, validation by the council, then the council decision, which for a householder application has a statutory period of 8 weeks from the day after the council receives a valid application.Enquiry and constraints checkRoute chosen, fixed quote sentMeasured surveyThe house as it stands, on one datumDrawingsAbout 7 days after the surveyYou approve the designFrozen in writingIndependent checkA second technologist checks every sheetSubmissionForms, plans and fee to the councilValidationThe council confirms the application is completeDecisionHouseholder: 8 weeks from a valid application
Fig. 1 From first enquiry to a planning decision · Source: Planning Practice Guidance: determining a planning application (GOV.UK)

The two fees per request

The council’s fee is charged for each request, not for each condition. The national schedule sets it at £89 where the request relates to householder development, and £309 in any other case.

That is why our pack covers up to three conditions in one go: it lets you group related conditions into a single request where the council accepts it. We tell you in advance how many requests your permission needs.

How long the council has

The guidance says the council must give notice of its decision within 8 weeks, beginning with the day after the request is received, or a longer period agreed in writing. If no decision is made within 12 weeks, it must return the fee.

If the council runs out of time, a deemed discharge may be available under the 2015 Development Management Procedure Order. We show you the route if it arises, but a deemed discharge is for when you are close to starting, not a substitute for a good first submission.

Why the details have to be right first time

A refused request still costs the fee. The guidance notes that there is a right of appeal where a request is refused or not decided in time, but an appeal is slow compared with fixing the details.

Our pack puts each condition’s requirement beside the drawing or document that answers it, so the officer sees the answer on the first page. If the permission was granted on a pre-commencement basis, the council needed your written agreement to that condition before imposing it, which is worth knowing if one seems unreasonable.

Listed building consent is different: GOV.UK lists a discharge of a condition on a listed building consent among those with no application fee.

By the numbers

Discharge of conditions costs: common questions

Can I start work while the request is being decided?

Not if the condition says nothing may start until it is discharged. Building early is unlawful and can be enforced against, so wait for the written decision.

Source: Use of planning conditions, planning practice guidance (GOV.UK)

What if the permission has more than three conditions?

Then it needs more than one pack, or a larger fee agreed in advance. We list each condition and its requirement before you pay, so the cost is clear.

Is the council fee refunded if they refuse?

No. The fee is returned only if no decision is made within 12 weeks. That is why the submission has to meet each condition’s wording first time.

Source: Use of planning conditions, planning practice guidance (GOV.UK)

Sources

  1. Use of planning conditions, planning practice guidance (GOV.UK)
  2. Planning fees: annual indexation from 1 April 2026 (GOV.UK)
  3. Fees for planning applications: applications that need no fee (GOV.UK)
  4. Town and Country Planning Act 1990, section 100ZA: pre-commencement conditions (legislation.gov.uk)

About the author. Ben Shaukat is Managing Director of Property Architecture Ltd, which trades as Planning Drawings.

Published by Planning Drawings. Checked against the sources above on . Planning rules change; check your council before you build.

Discharge of planning conditions

from £325

Fixed fee
£325
VAT
None to add

£325. A starting fee: we confirm one fixed figure after checking your address. The council’s own fee, where there is one, is paid to the council.

Get my fixed fee

Ask for a fixed fee for your drawings

Tell us the address and what you have in mind. We check the property and reply with the route and a fixed fee, no VAT to add.

Call 020 7131 9705WhatsApp +44 7592 201353

Back to the form